# Delivery report

Source: https://projectfeed.app/docs/analytics/delivery

Compare completed and created tasks, cycle time, and open work.

-   [Plan Pro or Enterprise](https://projectfeed.app/docs/billing)
-   Who Owners and admins; project members see project reports

## Review task progress

Open Delivery to compare completed and created tasks. The top figures are Completed, Cycle time · P50 (the median, with P85 shown alongside it), Open, Overdue, and Oldest open. P85 appears once at least 5 tasks have a cycle time.

Delivery trajectory plots cumulative tasks completed over the range and projects the next 30 days from the last 14 days of completions, with figures for the next 7 days, the next 30 days, and the rest of the quarter. When open work grew over the range, the open work card says the backlog is growing instead of estimating a clear date. Faded Throughput bars mark partial weeks at the start and end of the range. Below it, the report shows weekly throughput, cumulative flow, aging tasks, task mix, and completions by assignee. In cumulative flow, Done in period counts only tasks finished during the range.

## Fix delivery report questions

The forecast is missing

A forecast needs a range of 3 to 400 days that includes today and complete task history. Choose a range such as Last 30 days.

Cumulative flow is missing

The report leaves out cumulative flow when the status history for the range is incomplete. The other charts still use the data that is available.

Completions by assignee add up to less than Completed

For some tasks the assignee at the time of completion cannot be determined, so those tasks are not credited to a person.